Project Status Dashboard
Road To Mobilization
BOKA PRIDE Mobilization
Road To Mobilization
MERMAID RESILIENT Mobilization
Project Picture
At-a-glance status
Road To Mobcompletion percentage101 / 101 completedNext 30 Daysactivities starting0 critical in windowMDRIAF issued168 IFR / 69 pending returnProcurement Trackingitems complete9 procurement attention itemsPMSrows complete43 critical delay / 611 rowsS-Curve AreasIRONG TIMURIT 60.5% / KM 55.5% / BE 64.0%
Manhours
Total Manhours
| Package | Platform | Last Week Cumulative | This Week | Total Cumulative |
|---|---|---|---|---|
| PACKAGE A | Irong Timur | 74,980 | 10,728 | 85,708 |
| PACKAGE A | Kurma Manis | 56,772 | 4,764 | 61,536 |
| PACKAGE B | Berantai East | 23,384 | 533 | 23,917 |
| PACKAGE A | Total | 131,752 | 15,492 | 147,244 |
| PACKAGE B | Total | 23,384 | 533 | 23,917 |
| Overall | Total | 155,136 | 16,025 | 171,161 |
Road To Mobilization
Top 10 RTM Issues
No active RTM issuesRows with issue remarks will appear here after the RTM workbook is updated.
Execution
Schedule
Next 30 Days
Documentation
MDR
Top 10 Pending IFR
- Anchor Pattern Procedure and Mooring AnalysisKURMA MANIS / T&I / target 17 Apr 2026 / Overdue
- Crossing Installation ProcedureKURMA MANIS / T&I / target 15 Jun 2026 / Overdue
- Pre-Lay Survey ReportIRONG TIMUR / T&I / target 15 Jun 2026 / Overdue
- Pre-Lay Survey ReportKURMA MANIS / T&I / target 15 Jun 2026 / Overdue
- Pre-Lay Survey ReportBERANTAI EAST / T&I / target 15 Jun 2026 / Overdue
- Crossing Arrangements DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
- Crossing Material Installation Rigging Detail, Work Sequence and othersBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
- Flexible FPSO I-Tube Pull-in Arrangement DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
- Flexible I-Tube Installation Arrangement DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
- Flexible Lay Spread and Sea Fastening DesignBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
Top 10 Pending IAF
- Offshore Emergency Response PlanBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
- Scaffolding & Working at Height ProcedureBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
- Crossing Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
- Diverless Tie-In Spools Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
- Pre-Lay Survey ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
- Subsea Pipeline Installation AnalysisIRONG TIMUR / T&I / target 30 Mar 2026
- Subsea Pipeline Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
- Zap-Lok Joint Validation Test Procedure ReportIRONG TIMUR / T&I / target 30 Mar 2026
- Spool & Riser Transportation and Seafastening AnalysisIRONG TIMUR / T&I / target 08 Apr 2026
- Linepipe Transportation and Seafastening AnalysisIRONG TIMUR / T&I / target 09 Apr 2026
Progress Curve
S-Curve
IRONG TIMUR S-CurveLatest 24 Jul 2026
60.5% Actual92.7% Plan-32.2% Variance+8.3% Last movement39.5% Remaining
Monthly IncrementActual progress added each period
Selected Reading
- IRONG TIMURActual 60.5% / Plan 92.7% / Variance -32.2%
Actual vs Plan
PTR Status
Procurement Tracking
HATFLEXPackage B / 9 items / 0 complete
1 criticalActual88.9%Plan96.8%Variance-7.9%
- No weekly update recorded.
Marubeni-Itochu Tubulars Asia Pte Ltd (TPCO)Package A / 2 items / 2 complete
On trackActual100.0%Plan100.0%Variance0.0%
- LinePipe - Pipeline: Delivered
- LinePipe - Riser and Spool: Delivered
OceaneeringPackage A / 2 items / 2 complete
On trackActual100.0%Plan100.0%Variance0.0%
- Riser Hub Connector (Package 1): Delivered
AISPackage B / 1 items / 0 complete
On trackActual99.0%Plan96.8%Variance2.2%
- No weekly update recorded.
CFM TechnologiesPackage A / 1 items / 0 complete
On trackActual98.7%Plan100.0%Variance-1.3%
- Diverless Tie In System (RSAS+SDDC): Fabrication is ongoing
CHONG YUAN KAIPackage A / 1 items / 1 complete
On trackActual100.0%Plan100.0%Variance0.0%
- Flanges And Fitting: Delivered
No vendorPackage A / 1 items / 1 complete
On trackActual100.0%Plan100.0%Variance0.0%
- Riser Clamps Material and Stubs: 1st Truck - 22/04 ✅ (Riser Clamp Material) 2nd Truck - 23/04 ✅ (Riser Clamp Material) 3rd Truck - 23/04 ✅ (Riser Clamp Material) 4th Truck --> 2/6 ⌛(Riser Clamp Material batch 2)
PipeshieldPackage A / 1 items / 1 complete
On trackActual100.0%Plan100.0%Variance0.0%
- Crossing Sleepers & Concrete Matresses: Delivery Expected 1st of June