Project Status Dashboard
Road To Mobilization
BOKA PRIDE Mobilization
Road To Mobilization
MERMAID RESILIENT Mobilization
Project Picture
At-a-glance status
Road To Mobcompletion percentage34 / 121 completedNext 30 Daysactivities starting0 critical in windowMDRIAF issued156 IFR / 59 pending returnProcurement Trackingitems complete11 procurement attention itemsPMSrows complete91 critical delay / 611 rowsS-Curve AreasIRONG TIMURIT 47.6% / KM 48.4% / BE 46.6%
Manhours
Total Manhours
| Package | Platform | Last Week Cumulative | This Week | Total Cumulative |
|---|---|---|---|---|
| PACKAGE A | Irong Timur | 40,653 | 1,127 | 41,780 |
| PACKAGE A | Kurma Manis | 35,421 | 1,127 | 36,548 |
| PACKAGE B | Berantai East | 19,721 | 465 | 20,186 |
| PACKAGE A | Total | 76,074 | 2,254 | 78,328 |
| PACKAGE B | Total | 19,721 | 465 | 20,186 |
| Overall | Total | 95,795 | 2,719 | 98,514 |
Road To Mobilization
Top 10 RTM Issues
1Joint Review with VESTIGO and MWS by next week (16/6 or 18/6)1.01 / Procedure / B-WHP Riser Installation Procedure using Boka Pride2Pending Return from VPSB1.09 / Procedure / Survey & Positioning procedure3Pending from TUAH2.04 / Drawing / B-WHP Riser clamp & hanger clamp specific lifting rigging by Boka Pride4To follow up with HSE Requirement guideline for Lifting (General or Engineered Lifting)2.07 / Drawing / B-WHP riser hanger clamp transfer to B-WHP Platform sequence5Pending Engineering analysis from Azni Team2.08 / Drawing / B-WHP Topside winch sea fastening details6pending item 2.082.09 / Drawing / Boka Pride vessel setup for equipment setup and transfer operation7TISB To provide anchor details to CSS - storyboard2.12 / Drawing / DMA installation sequence by Boka Pride including the Soak test and DMA wire cutting8Material Ready Stock to received by 30/6
Seafatening ready on the same time.4.01 / Procurement and rental / Topside winch supply and services9Pending VO from Procurement.4.07 / Procurement and rental / Bolt Tensioning, Torque Tool, Hyd Impact Wrench, Pnuematic Impact Wrench Supply And Services10RFQ Stage, require expedite TBE, CBE and PO issuance by 19/64.09 / Procurement and rental / Procurement of DMA rigging
Execution
Schedule
Next 30 Days
Documentation
MDR
Top 10 Pending IFR
- Project HSEMS Bridging DocumentKURMA MANIS / HSE / target 23 Jan 2026 / Overdue
- Project Construction and Installation Risk AssessmentKURMA MANIS / HSE / target 20 Feb 2026 / Overdue
- Diverless Tie-In Spools Installation ProcedureKURMA MANIS / T&I / target 11 Mar 2026 / Overdue
- Intelligent PIG (IP) Baseline Survey ProcedureIRONG TIMUR / T&I / target 30 Mar 2026 / Overdue
- Intelligent PIG (IP) Baseline Survey ProcedureKURMA MANIS / T&I / target 30 Mar 2026 / Overdue
- Anchor Pattern Procedure and Mooring AnalysisKURMA MANIS / T&I / target 17 Apr 2026 / Overdue
- Flexible I-Tube Installation Arrangement DrawingsBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
- Flexible Lay Spread and Sea Fastening DesignBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
- Flexible Lay spread System Sea Fastening Design and Transportation Analysis ReportBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
- Flexible Pipeline, Ancillaries & Mattress Transportation and Seafastening AnalysisBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
Top 10 Pending IAF
- Line Pipes Manfacturing HandbookIRONG TIMUR / T&I / target 23 Jan 2026 / waiting return
- Line Pipes Manfacturing HandbookKURMA MANIS / T&I / target 23 Jan 2026 / waiting return
- Offshore Emergency Response PlanBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
- Scaffolding & Working at Height ProcedureBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
- Barge Management System (BMS) and Tug Management System (TMS) ProcedureIRONG TIMUR / T&I / target 27 Feb 2026 / waiting return
- Blasting and Painting ProcedureKURMA MANIS / QAQC / target 24 Apr 2026 / waiting return
- Job Hazard AnalysisIRONG TIMUR / HSE / target 24 Apr 2026 / waiting return
- Job Hazard AnalysisKURMA MANIS / HSE / target 24 Apr 2026 / waiting return
- Onshore Emergency Response PlanIRONG TIMUR / HSE / target 24 Apr 2026 / waiting return
- Onshore Emergency Response PlanKURMA MANIS / HSE / target 24 Apr 2026 / waiting return
Progress Curve
S-Curve
IRONG TIMUR S-CurveLatest 12 Jun 2026
47.6% Actual60.1% Plan-12.4% Variance+1.6% Last movement52.4% Remaining
Monthly IncrementActual progress added each period
Selected Reading
- IRONG TIMURActual 47.6% / Plan 60.1% / Variance -12.4%
Actual vs Plan
PTR Status
Procurement Tracking
HATFLEXPackage B / 9 items / 0 complete
7 criticalActual49.7%Plan68.7%Variance-19.0%
- No weekly update recorded.
No vendorPackage A / Package B / 17 items / 15 complete
2 criticalActual93.2%Plan97.4%Variance-4.1%
- Riser Clamps Material and Stubs: 1st Truck - 22/04 ✅ (Riser Clamp Material) 2nd Truck - 23/04 ✅ (Riser Clamp Material) 3rd Truck - 23/04 ✅ (Riser Clamp Material) 4th Truck --> 2/6 ⌛(Riser Clamp Material batch 2)
- Sub-Contractor - Fabrication: Procurement stage for TBE.
CFM TechnologiesPackage A / 1 items / 0 complete
1 criticalActual72.9%Plan100.0%Variance-27.1%
- Diverless Tie In System (RSAS+SDDC): Fabrication is ongoing
WascoPackage A / 1 items / 0 complete
1 criticalActual48.4%Plan100.0%Variance-51.6%
- External Corrosion Coating - Pipeline,Riser and Bends: PQT activities on going - Bends PQT scheduled on 17 March - Neoprene PQT scheduled on 31 March
Marubeni-Itochu Tubulars Asia Pte Ltd (TPCO)Package A / 2 items / 2 complete
On trackActual100.0%Plan100.0%Variance0.0%
- LinePipe - Pipeline: Delivered
- LinePipe - Riser and Spool: Delivered
OceaneeringPackage A / 2 items / 2 complete
On trackActual100.0%Plan100.0%Variance0.0%
- Riser Hub Connector (Package 1): Delivered
Saliran GroupPackage A / 2 items / 2 complete
On trackActual100.0%Plan100.0%Variance0.0%
- 12inch Hanger Flange: Delivered
- Hot Induction Bends: Bends delivered to WASCO
AISPackage B / 1 items / 0 complete
On trackActual98.5%Plan79.7%Variance18.8%
- No weekly update recorded.