Project Status Dashboard

Updated as of 16 Jun 2026

Road To Mobilization

BOKA PRIDE Mobilization

Road to mobilization target: 23 Jun 2026

2Days
:
02Hours
:
26Minutes
:
27Seconds

Road To Mobilization

MERMAID RESILIENT Mobilization

Road to mobilization target: 11 Jul 2026

20Days
:
02Hours
:
26Minutes
:
27Seconds

Project Picture

At-a-glance status

Manhours

Total Manhours

Updated as of 05 Jun 2026

Overall98,5142,719 this week
PACKAGE A78,3282,254 this week
PACKAGE B20,186465 this week
PackagePlatformLast Week CumulativeThis WeekTotal Cumulative
PACKAGE AIrong Timur40,6531,12741,780
PACKAGE AKurma Manis35,4211,12736,548
PACKAGE BBerantai East19,72146520,186
PACKAGE ATotal76,0742,25478,328
PACKAGE BTotal19,72146520,186
OverallTotal95,7952,71998,514

Road To Mobilization

Top 10 RTM Issues

38 issues flagged / showing 10

Open RTM

Execution

Schedule

Next 30 days: 01 Jun 2026 to 01 Jul 2026 / full schedule 01 Jun 2026 to 06 Dec 2026

Open schedule
Next 30 days11activities starting in window
Critical0critical activities in window
Activities12752 summary lines

Next 30 Days

  • Jacket CleaningOther / 05 Jun to 15 Jun
  • Rig-UpIrong Timur / 06 Jun to 12 Jun
  • Drilling @ Kurma Manis WHPIrong Timur / 12 Jun to 21 Jul
  • Onhire @ SingaporeOther / 20 Jun to 20 Jun
  • Transit from Singapore to JohorOther / 20 Jun to 21 Jun
  • SAMAKOther / 21 Jun to 22 Jun
  • Offshore Med. Checkup for BOKA PRIDE POBOther / 21 Jun to 27 Jun
  • Bunkering @ JohorOther / 22 Jun to 23 Jun
  • Rigup ROV + ADS + Concrete Matteres + Sleepers + RSAS + Survey Equipment + Spool LoadoutOther / 23 Jun to 01 Jul
  • SeafasteningOther / 24 Jun to 01 Jul

Documentation

MDR

203 MDR documents / Updated as of 12 Jun 2026

Open MDR
Documents203BERANTAI EAST / IRONG TIMUR / KURMA MANIS
IFR issued77%156 of 203
Pending return59IFR issued, return not received
IAF issued33%68 of 203

Top 10 Pending IFR

  • Project HSEMS Bridging DocumentKURMA MANIS / HSE / target 23 Jan 2026 / Overdue
  • Project Construction and Installation Risk AssessmentKURMA MANIS / HSE / target 20 Feb 2026 / Overdue
  • Diverless Tie-In Spools Installation ProcedureKURMA MANIS / T&I / target 11 Mar 2026 / Overdue
  • Intelligent PIG (IP) Baseline Survey ProcedureIRONG TIMUR / T&I / target 30 Mar 2026 / Overdue
  • Intelligent PIG (IP) Baseline Survey ProcedureKURMA MANIS / T&I / target 30 Mar 2026 / Overdue
  • Anchor Pattern Procedure and Mooring AnalysisKURMA MANIS / T&I / target 17 Apr 2026 / Overdue
  • Flexible I-Tube Installation Arrangement DrawingsBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
  • Flexible Lay Spread and Sea Fastening DesignBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
  • Flexible Lay spread System Sea Fastening Design and Transportation Analysis ReportBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue
  • Flexible Pipeline, Ancillaries & Mattress Transportation and Seafastening AnalysisBERANTAI EAST / T&I / target 20 Apr 2026 / Overdue

Top 10 Pending IAF

  • Line Pipes Manfacturing HandbookIRONG TIMUR / T&I / target 23 Jan 2026 / waiting return
  • Line Pipes Manfacturing HandbookKURMA MANIS / T&I / target 23 Jan 2026 / waiting return
  • Offshore Emergency Response PlanBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
  • Scaffolding & Working at Height ProcedureBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
  • Barge Management System (BMS) and Tug Management System (TMS) ProcedureIRONG TIMUR / T&I / target 27 Feb 2026 / waiting return
  • Blasting and Painting ProcedureKURMA MANIS / QAQC / target 24 Apr 2026 / waiting return
  • Job Hazard AnalysisIRONG TIMUR / HSE / target 24 Apr 2026 / waiting return
  • Job Hazard AnalysisKURMA MANIS / HSE / target 24 Apr 2026 / waiting return
  • Onshore Emergency Response PlanIRONG TIMUR / HSE / target 24 Apr 2026 / waiting return
  • Onshore Emergency Response PlanKURMA MANIS / HSE / target 24 Apr 2026 / waiting return

Progress Curve

S-Curve

Open S-curve
IRONG TIMUR S-CurveLatest 12 Jun 2026
47.6% Actual60.1% Plan-12.4% Variance+1.6% Last movement52.4% Remaining
Monthly IncrementActual progress added each period

Selected Reading

  • IRONG TIMURActual 47.6% / Plan 60.1% / Variance -12.4%

Actual vs Plan

Actual48%
Plan60%

PTR Status

Procurement Tracking

Open PTR
HATFLEXPackage B / 9 items / 0 complete
7 critical
Actual49.7%Plan68.7%Variance-19.0%
Actual50%
  • No weekly update recorded.
No vendorPackage A / Package B / 17 items / 15 complete
2 critical
Actual93.2%Plan97.4%Variance-4.1%
Actual93%
  • Riser Clamps Material and Stubs: 1st Truck - 22/04 ✅ (Riser Clamp Material) 2nd Truck - 23/04 ✅ (Riser Clamp Material) 3rd Truck - 23/04 ✅ (Riser Clamp Material) 4th Truck --> 2/6 ⌛(Riser Clamp Material batch 2)
  • Sub-Contractor - Fabrication: Procurement stage for TBE.
CFM TechnologiesPackage A / 1 items / 0 complete
1 critical
Actual72.9%Plan100.0%Variance-27.1%
Actual73%
  • Diverless Tie In System (RSAS+SDDC): Fabrication is ongoing
WascoPackage A / 1 items / 0 complete
1 critical
Actual48.4%Plan100.0%Variance-51.6%
Actual48%
  • External Corrosion Coating - Pipeline,Riser and Bends: PQT activities on going - Bends PQT scheduled on 17 March - Neoprene PQT scheduled on 31 March
Marubeni-Itochu Tubulars Asia Pte Ltd (TPCO)Package A / 2 items / 2 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • LinePipe - Pipeline: Delivered
  • LinePipe - Riser and Spool: Delivered
OceaneeringPackage A / 2 items / 2 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • Riser Hub Connector (Package 1): Delivered
Saliran GroupPackage A / 2 items / 2 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • 12inch Hanger Flange: Delivered
  • Hot Induction Bends: Bends delivered to WASCO
AISPackage B / 1 items / 0 complete
On track
Actual98.5%Plan79.7%Variance18.8%
Actual99%
  • No weekly update recorded.