Project Status Dashboard

Updated as of 07 Jul 2026

Road To Mobilization

BOKA PRIDE Mobilization

Mobilization target date has arrived.

0Days
:
00Hours
:
00Minutes
:
00Seconds

Road To Mobilization

MERMAID RESILIENT Mobilization

Mobilization target date has arrived.

0Days
:
00Hours
:
00Minutes
:
00Seconds

Project Picture

At-a-glance status

Manhours

Total Manhours

Updated as of 24 Jul 2026

Overall171,16116,025 this week
PACKAGE A147,24415,492 this week
PACKAGE B23,917533 this week
PackagePlatformLast Week CumulativeThis WeekTotal Cumulative
PACKAGE AIrong Timur74,98010,72885,708
PACKAGE AKurma Manis56,7724,76461,536
PACKAGE BBerantai East23,38453323,917
PACKAGE ATotal131,75215,492147,244
PACKAGE BTotal23,38453323,917
OverallTotal155,13616,025171,161

Road To Mobilization

Top 10 RTM Issues

No RTM issues flagged

Open RTM
No active RTM issuesRows with issue remarks will appear here after the RTM workbook is updated.

Execution

Schedule

Next 30 days: 01 Jun 2026 to 01 Jul 2026 / full schedule 01 Jun 2026 to 25 Oct 2026

Open schedule
Next 30 days11activities starting in window
Critical0critical activities in window
Activities15657 summary lines

Next 30 Days

  • Rig-UpOther / 06 Jun to 12 Jun
  • Jacket CleaningOther / 12 Jun to 23 Jun
  • Onhire @ SingaporeOther / 17 Jun to 17 Jun
  • Transit from Singapore to JohorOther / 17 Jun to 18 Jun
  • SAMAKOther / 18 Jun to 19 Jun
  • Bunkering @ JohorOther / 19 Jun to 20 Jun
  • Offshore Med. Checkup for BOKA PRIDE POBOther / 20 Jun to 21 Jun
  • Rigup ROV + ADS + Concrete Matteres + Sleepers + RSAS + Survey Equipment LoadoutOther / 20 Jun to 30 Jun
  • SeafasteningOther / 20 Jun to 30 Jun
  • Mobilization POBOther / 29 Jun to 30 Jun

Documentation

MDR

207 MDR documents / Updated as of 29 Jun 2026

Open MDR
Documents207BERANTAI EAST / IRONG TIMUR / KURMA MANIS
IFR issued81%168 of 207
Pending return69IFR issued, return not received
IAF issued11%23 of 207

Top 10 Pending IFR

  • Anchor Pattern Procedure and Mooring AnalysisKURMA MANIS / T&I / target 17 Apr 2026 / Overdue
  • Crossing Installation ProcedureKURMA MANIS / T&I / target 15 Jun 2026 / Overdue
  • Pre-Lay Survey ReportIRONG TIMUR / T&I / target 15 Jun 2026 / Overdue
  • Pre-Lay Survey ReportKURMA MANIS / T&I / target 15 Jun 2026 / Overdue
  • Pre-Lay Survey ReportBERANTAI EAST / T&I / target 15 Jun 2026 / Overdue
  • Crossing Arrangements DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
  • Crossing Material Installation Rigging Detail, Work Sequence and othersBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
  • Flexible FPSO I-Tube Pull-in Arrangement DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
  • Flexible I-Tube Installation Arrangement DrawingsBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue
  • Flexible Lay Spread and Sea Fastening DesignBERANTAI EAST / T&I / target 19 Jun 2026 / Overdue

Top 10 Pending IAF

  • Offshore Emergency Response PlanBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
  • Scaffolding & Working at Height ProcedureBERANTAI EAST / HSE / target 13 Feb 2026 / waiting return
  • Crossing Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
  • Diverless Tie-In Spools Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
  • Pre-Lay Survey ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
  • Subsea Pipeline Installation AnalysisIRONG TIMUR / T&I / target 30 Mar 2026
  • Subsea Pipeline Installation ProcedureIRONG TIMUR / T&I / target 30 Mar 2026
  • Zap-Lok Joint Validation Test Procedure ReportIRONG TIMUR / T&I / target 30 Mar 2026
  • Spool & Riser Transportation and Seafastening AnalysisIRONG TIMUR / T&I / target 08 Apr 2026
  • Linepipe Transportation and Seafastening AnalysisIRONG TIMUR / T&I / target 09 Apr 2026

Progress Curve

S-Curve

Open S-curve
IRONG TIMUR S-CurveLatest 24 Jul 2026
60.5% Actual92.7% Plan-32.2% Variance+8.3% Last movement39.5% Remaining
Monthly IncrementActual progress added each period

Selected Reading

  • IRONG TIMURActual 60.5% / Plan 92.7% / Variance -32.2%

Actual vs Plan

Actual60%
Plan93%

PTR Status

Procurement Tracking

Open PTR
HATFLEXPackage B / 9 items / 0 complete
1 critical
Actual88.9%Plan96.8%Variance-7.9%
Actual89%
  • No weekly update recorded.
Marubeni-Itochu Tubulars Asia Pte Ltd (TPCO)Package A / 2 items / 2 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • LinePipe - Pipeline: Delivered
  • LinePipe - Riser and Spool: Delivered
OceaneeringPackage A / 2 items / 2 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • Riser Hub Connector (Package 1): Delivered
AISPackage B / 1 items / 0 complete
On track
Actual99.0%Plan96.8%Variance2.2%
Actual99%
  • No weekly update recorded.
CFM TechnologiesPackage A / 1 items / 0 complete
On track
Actual98.7%Plan100.0%Variance-1.3%
Actual99%
  • Diverless Tie In System (RSAS+SDDC): Fabrication is ongoing
CHONG YUAN KAIPackage A / 1 items / 1 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • Flanges And Fitting: Delivered
No vendorPackage A / 1 items / 1 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • Riser Clamps Material and Stubs: 1st Truck - 22/04 ✅ (Riser Clamp Material) 2nd Truck - 23/04 ✅ (Riser Clamp Material) 3rd Truck - 23/04 ✅ (Riser Clamp Material) 4th Truck --> 2/6 ⌛(Riser Clamp Material batch 2)
PipeshieldPackage A / 1 items / 1 complete
On track
Actual100.0%Plan100.0%Variance0.0%
Actual100%
  • Crossing Sleepers & Concrete Matresses: Delivery Expected 1st of June