Master Deliverables Register

PACKAGE-A-MDR_260612.xlsm + PACKAGE-B-MDR-260612.xlsm / 203 documents / BERANTAI EAST / IRONG TIMUR / KURMA MANIS

Updated as of 12 Jun 2026
Documents203visible MDR records
IFR issued77%156 of 203
Pending return59IFR issued, return not received
IAF issued33%68 of 203
Overdue157forecast due before as-of date

Progress by Area

203 visible records across 3 area(s)

IFR cycleIssue for review
77%Issued
156of 203
Returned97/156
Awaiting return59/203
MWS reviewMarine warranty survey
70%Submitted
59of 84
Required84/203
Returned39/84
Final closeoutIssued for construction
33%IAF issued
68of 203
Final return38/68
Overdue157/203

Discipline Load

5 visible discipline group(s)

T&I13%
QAQC67%
HSE13%
PMT100%
PRO100%

MDR Documents

203 visible of 203 MDR documents

CompletePendingOverdue
LocationDisciplineDoc / DWG No.DeliverableIFRReturnMWSIAFFinal ReturnStatus
IRONG TIMURPMTTISB-IRG1_RPS-PMT-QEP-0001Project Execution Plan (PEP)PROJECT MANAGEMENT
Issued19 Sep 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued22 Jan 2026Rev 0
PendingForecast 29 Jan 2026
Final return overdueFinal return: 29 Jan 2026
IRONG TIMURPMTTISB-IRG1_RPS-PMT-RPT-0001Planning PackagePROJECT MANAGEMENT
Issued12 Feb 2026Rev A
Returned16 Mar 2026Code A
N/A
Issued22 Apr 2026Rev 0
Returned01 May 2026Code 1
Closed
IRONG TIMURPMTTISB-IRG1_RPS-PMT-RPT-0002Project SchedulePROJECT MANAGEMENT
Issued19 Sep 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued23 Dec 2025Rev 0
PendingForecast 30 Dec 2025
Final return overdueFinal return: 30 Dec 2025
IRONG TIMURPMTTISB-IRG1_RPS-PMT-QPR-0001Final Documentation ProcedurePROJECT MANAGEMENT
Issued03 Oct 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued14 Nov 2025Rev 0
PendingForecast 21 Nov 2025
Final return overdueFinal return: 21 Nov 2025
IRONG TIMURPMTTISB-IRG1_RPS-PMT-MDR-0001Master Deliverables RegisterPROJECT MANAGEMENT
Issued12 Sep 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued23 Oct 2025Rev 0
Returned10 Dec 2025Code 0
Closed
IRONG TIMURPROTISB-IRG1_RPS-SCM-QPR-0001Procurement Plan and ProcedurePROCUREMENT
Issued10 Oct 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued08 Dec 2025Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QQP-0001Project Quality Plan (PQP)QA/QC
Issued19 Sep 2025Rev A
Returned29 Oct 2025Code A
N/A
Issued24 Oct 2025Rev 0
Returned10 Dec 2025Code 0
Closed
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QTP-0001Inspection Test Plan (ITP) for Pipeline InstallationQA/QC
Issued25 Apr 2026Rev A
Returned11 May 2026Code A
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QTP-0002Inspection Test Plan (ITP) for Riser and Spools FabricationQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0001Welding Qualification Test Procedure (WQT)QA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0002Welding Procedure Specifications (WPS) for StructureQA/QC
Issued14 Jan 2026Rev A
Returned05 May 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0003Welding Procedure Specifications (WPS) for Spool Tie-inQA/QC
Issued14 Jan 2026Rev A
Returned05 May 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0004Weld Repair ProcedureQA/QC
Issued04 Feb 2026Rev A
Returned05 May 2026Code A
N/A
Issued14 May 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0005Welding Consumable Control ProcedureQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0006Blasting and Painting ProcedureQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued03 Jun 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-RPT-0001Paint MatrixQA/QC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0008Non-Destructive Examination (NDE) Procedure for Tie-in, Seafastening & Minor FabricationQA/QC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
Issued14 May 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-RPT-0002NDE MatrixQA/QC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0009Non-Conformance Control ProcedureQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0010Corrective Action ProcedureQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-RPT-0003CV and Qualification Records of NDE PersonnelQA/QC
Issued22 Apr 2026Rev A
PendingForecast 29 Apr 2026
N/A
PendingForecast 08 May 2026
PendingForecast -
Client return overdueClient return: 29 Apr 2026 / IAF: 08 May 2026
IRONG TIMURQAQCTISB-IRG1_RPS-QAC-QPR-0011Material Control ProcedureQA/QC
Issued06 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
PendingForecast 12 Dec 2025
Final return overdueFinal return: 12 Dec 2025
IRONG TIMURHSETISB-IRG1_RPS-HSE-HHP-0001HSE PlanHSE
Issued20 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
Returned19 Feb 2026Code 0
Closed
IRONG TIMURHSETISB-IRG1_RPS-HSE-HMP-0001Project HSEMS Bridging DocumentHSE
Issued21 Oct 2025Rev A
Returned09 Jun 2026Code 2
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-QPR-0001Offshore Emergency Response PlanHSE
Issued05 May 2026Rev A
PendingForecast 12 May 2026
Returned11 May 2026Code 1
PendingForecast 08 May 2026
PendingForecast -
Client return overdueClient return: 12 May 2026 / IAF: 08 May 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-QPR-0002Onshore Emergency Response PlanHSE
Issued07 Apr 2026Rev A
PendingForecast 14 Apr 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 14 Apr 2026 / IAF: 24 Apr 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-HHA-0001Project Construction and Installation Risk AssessmentHSE
PendingForecast 15 May 2026
PendingForecast -
N/A
PendingForecast 01 Jun 2026
PendingForecast -
IFR overdueIFR: 15 May 2026 / IAF: 01 Jun 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-HHA-0002Job Hazard AnalysisHSE
Issued02 Mar 2026Rev A
PendingForecast 09 Mar 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 09 Mar 2026 / IAF: 24 Apr 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-QPR-0003Scaffolding & Working at Height ProcedureHSE
Issued07 Jan 2026Rev A
Returned02 May 2026Code 2
N/A
PendingForecast 24 Apr 2026
PendingForecast -
IAF overdueIAF: 24 Apr 2026
IRONG TIMURHSETISB-IRG1_RPS-HSE-QPR-0004Waste Management Plan & ProcedureHSE
Issued20 May 2026Rev A
PendingForecast -
N/A
PendingForecast 11 May 2026
PendingForecast -
IAF overdueIAF: 11 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QMU-0001Line Pipes Manfacturing HandbookTRANSPORTATION & INSTALLATION
Issued14 Apr 2026Rev A
PendingForecast 21 Apr 2026
N/A
PendingForecast 23 Jan 2026
PendingForecast -
Client return overdueClient return: 21 Apr 2026 / IAF: 23 Jan 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QMU-0002Line Pipes Coating HandbookTRANSPORTATION & INSTALLATION
PendingForecast 15 Jun 2026
PendingForecast -
N/A
PendingForecast 04 May 2026
PendingForecast -
IAF overdueIAF: 04 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QMU-0003Zap-Lok End Prepration Manfacturing BookTRANSPORTATION & INSTALLATION
PendingForecast 15 Jun 2026
PendingForecast -
N/A
PendingForecast 06 Mar 2026
PendingForecast -
IAF overdueIAF: 06 Mar 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-EMS-0001Riser and Spools Fabrication PackageTRANSPORTATION & INSTALLATION
PendingForecast 15 Jun 2026
PendingForecast -
N/A
PendingForecast 21 Jul 2026
PendingForecast -
Pending IFR
IRONG TIMURT&ITISB-IRG1_RPS-PIL-EMS-0002Diverless Tie-In System Fabrication PackageTRANSPORTATION & INSTALLATION
PendingForecast 15 Jun 2026
PendingForecast -
N/A
PendingForecast 27 Mar 2026
PendingForecast -
IAF overdueIAF: 27 Mar 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0001Zap-Lok Joint Validation Test Procedure ReportTRANSPORTATION & INSTALLATION
Issued13 Mar 2026Rev A
Returned02 Apr 2026Code 1
Returned30 Mar 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0010Zaplok Pipeline Repair ProcedureTRANSPORTATION & INSTALLATION
Issued06 May 2025Rev A
Returned09 Jun 2026Code 2
Returned25 May 2026Code 1
Issued03 Jun 2026Rev 0
PendingForecast -
IAF issued
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0001Vessel Pull Off / Out ProcedureTRANSPORTATION & INSTALLATION
Issued11 Apr 2026Rev A
Returned09 Apr 2026Code 2
Returned19 Apr 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0002Pipeline Offshore Mobilization ProcedureTRANSPORTATION & INSTALLATION
Issued18 May 2026Rev A
Returned02 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-RPT-0001Linepipe Transportation and Seafastening AnalysisTRANSPORTATION & INSTALLATION
Issued03 Mar 2026Rev A
Returned17 Mar 2026Code 2
Returned09 Apr 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-QPR-0001Linepipe Transportation and Handling ProcedureTRANSPORTATION & INSTALLATION
Issued25 Apr 2026Rev A
Returned02 Jun 2026Code 2
Returned29 Apr 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-RPT-0002Spool & Riser Transportation and Seafastening AnalysisTRANSPORTATION & INSTALLATION
Issued31 Mar 2026Rev A
Returned02 Apr 2026Code 2
Returned08 Apr 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-QPR-0002Spool & Riser Transportation and Handling ProcedureTRANSPORTATION & INSTALLATION
Issued18 May 2026Rev A
Returned02 Jun 2026Code 2
Returned25 May 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0002WHP Riser Installation AnalysisTRANSPORTATION & INSTALLATION
Issued05 Apr 2026Rev A
Returned02 Jun 2026Code 2
Returned09 Apr 2026Code 2
Issued17 May 2026Rev 0
Returned30 May 2026Code 2
Closed
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0003WHP Riser Installation ProcedureTRANSPORTATION & INSTALLATION
Issued14 Apr 2026Rev A
Returned09 Jun 2026Code 2
Submitted27 Apr 2026
PendingForecast 23 Jun 2026
PendingForecast -
MWS return overdueMWS return: 04 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0003Subsea Pipeline Installation AnalysisTRANSPORTATION & INSTALLATION
Issued05 Feb 2026Rev A
Returned03 Apr 2026Code 2
Returned30 Mar 2026Code 2
Issued23 Apr 2026Rev 0
Returned09 Jun 2026Code 2
Closed
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0004Subsea Pipeline Installation ProcedureTRANSPORTATION & INSTALLATION
Issued06 Mar 2026Rev A
Returned30 Mar 2026Code 2
Returned30 Mar 2026Code 2
Issued24 May 2026Rev 0
Returned09 Jun 2026Code 2
Closed
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0004Diverless Tie-In Spools Installation AnalysisTRANSPORTATION & INSTALLATION
PendingForecast 30 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 08 May 2026
PendingForecast -
IFR overdueIFR: 30 Apr 2026 / IAF: 08 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0005Diverless Tie-In Spools Installation ProcedureTRANSPORTATION & INSTALLATION
Issued18 Apr 2026Rev A
Returned14 Apr 2026Code 2
Returned30 Mar 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0009Anchor Handling ProcedureTRANSPORTATION & INSTALLATION
Issued06 Apr 2026Rev A
Returned14 Apr 2026Code 2
Returned17 Apr 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-RPT-0003Anchor Pattern Procedure and Mooring AnalysisTRANSPORTATION & INSTALLATION
Issued13 May 2026Rev A
Returned02 Jun 2026Code 2
Returned18 May 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0013Crossing Installation ProcedureTRANSPORTATION & INSTALLATION
Issued18 Mar 2026Rev A
Returned14 Apr 2026Code 2
Returned30 Mar 2026Code 2
Issued17 May 2026Rev 0
Returned22 May 2026Code 3
Closed
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0007Pre-Lay Survey ProcedureTRANSPORTATION & INSTALLATION
Issued06 Mar 2026Rev A
Returned18 Apr 2026Code 1
Returned30 Mar 2026Code 2
Issued16 Apr 2026Rev 0
Returned05 May 2026Code 0
Closed
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0005Pre-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 08 May 2026
PendingForecast 06 Jan 1900
N/A
PendingForecast 08 May 2026
PendingForecast -
IFR overdueIFR: 08 May 2026 / IAF: 08 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0008Barge Management System (BMS) and Tug Management System (TMS) ProcedureTRANSPORTATION & INSTALLATION
Issued16 Apr 2026Rev A
PendingForecast 23 Apr 2026
Submitted27 Apr 2026
PendingForecast 27 Feb 2026
PendingForecast 06 Jan 1900
Client return overdueClient return: 23 Apr 2026 / MWS return: 04 May 2026 / IAF: 27 Feb 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0015As -Built Survey ProcedureTRANSPORTATION & INSTALLATION
Issued15 Apr 2026Rev A
PendingForecast 22 Apr 2026
N/A
PendingForecast 29 May 2026
PendingForecast -
Client return overdueClient return: 22 Apr 2026 / IAF: 29 May 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0006Post-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 30 Jul 2026
PendingForecast -
N/A
PendingForecast 03 Aug 2026
PendingForecast -
Pending IFR
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0006Marine Growth Cleaning ProcedureTRANSPORTATION & INSTALLATION
Issued14 Apr 2026Rev A
Returned12 May 2026Code 1
N/A
Issued18 May 2026Rev 0
Returned02 Jun 2026Code 4
Closed
IRONG TIMURT&ITISB-IRG1_RPS-NAV-ELA-0002Mermaid Resiliant Anchor Pattern at Berantai WHP-A for Pipeline Start-UpTRANSPORTATION & INSTALLATION
Issued08 Apr 2026Rev A
PendingForecast 15 Apr 2026
Returned12 Apr 2026Code 3
PendingForecast 27 Apr 2026
PendingForecast -
Client return overdueClient return: 15 Apr 2026 / IAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-ELA-0003Mermaid Resiliant Anchor Pattern for Pipeline InstallationTRANSPORTATION & INSTALLATION
Issued08 Apr 2026Rev A
Returned18 Apr 2026Code 2
Returned14 Apr 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-ELA-0004Mermaid Resiliant Anchor Pattern at Irong Timur for Pipeline LaydownTRANSPORTATION & INSTALLATION
Issued08 Apr 2026Rev A
PendingForecast 15 Apr 2026
Returned12 Apr 2026Code 3
PendingForecast 27 Apr 2026
PendingForecast -
Client return overdueClient return: 15 Apr 2026 / IAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-NAV-ELA-0007Mermaid Resiliant Anchor Pattern for Riser Installation at Berantai WHP-A PlatformTRANSPORTATION & INSTALLATION
Issued28 May 2026Rev A
PendingForecast 04 Jun 2026
Submitted28 May 2026
PendingNo forecast
PendingForecast -
Client return overdueClient return: 04 Jun 2026 / MWS return: 04 Jun 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0014Rigid Pipeline Pre-Commissioning ProcedureTRANSPORTATION & INSTALLATION
Issued24 May 2026Rev A
Returned04 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0016Overall System Test and Pre-CommissioningTRANSPORTATION & INSTALLATION
Issued24 May 2026Rev A
Returned04 Jun 2026Code 2
N/A
PendingForecast 28 Apr 2026
PendingForecast -
IAF overdueIAF: 28 Apr 2026
IRONG TIMURT&ITISB-IRG1_RPS-PIL-RPT-0007PIG Loading and Inspection ReportTRANSPORTATION & INSTALLATION
PendingForecast 19 Sep 2026
PendingForecast -
N/A
PendingForecast 02 Oct 2026
PendingForecast -
Pending IFR
IRONG TIMURT&ITISB-IRG1_RPS-PIL-QPR-0012Intelligent PIG (IP) Baseline Survey ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 30 Mar 2026
PendingForecast -
N/A
PendingForecast 27 Apr 2026
PendingForecast -
IFR overdueIFR: 30 Mar 2026 / IAF: 27 Apr 2026
KURMA MANISPMTTISB-KRM_RPS-PMT-QEP-0001Project Execution Plan (PEP)PROJECT MANAGEMENT
Issued19 Sep 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued22 Jan 2026Rev 0
Returned27 May 2026Code 1
Closed
KURMA MANISPMTTISB-KRM_RPS-PMT-RPT-0001Planning PackagePROJECT MANAGEMENT
Issued12 Feb 2026Rev A
Returned15 Mar 2026Code A
N/A
Issued22 Apr 2026Rev 0
Returned06 May 2026Code 0
Closed
KURMA MANISPMTTISB-KRM_RPS-PMT-RPT-0002Project SchedulePROJECT MANAGEMENT
Issued19 Sep 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued23 Dec 2025Rev 0
PendingForecast 30 Dec 2025
Final return overdueFinal return: 30 Dec 2025
KURMA MANISPMTTISB-KRM_RPS-PMT-QPR-0001Final Documentation ProcedurePROJECT MANAGEMENT
Issued03 Oct 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued14 Nov 2025Rev 0
PendingForecast 21 Nov 2025
Final return overdueFinal return: 21 Nov 2025
KURMA MANISPMTTISB-KRM_RPS-PMT-MDR-0001Master Deliverables RegisterPROJECT MANAGEMENT
Issued12 Sep 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued23 Oct 2025Rev 0
Returned10 Dec 2025Code 0
Closed
KURMA MANISPROTISB-KRM_RPS-SCM-QPR-0001Procurement Plan and ProcedurePROCUREMENT
Issued10 Oct 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued08 Dec 2025Rev 0
PendingForecast 15 Dec 2025
Final return overdueFinal return: 15 Dec 2025
KURMA MANISQAQCTISB-KRM_RPS-QAC-QQP-0001Project Quality Plan (PQP)QAQC
Issued19 Sep 2025Rev A
Returned23 Oct 2025Code A
N/A
Issued24 Oct 2025Rev 0
Returned10 Dec 2025Code 0
Closed
KURMA MANISQAQCTISB-KRM_RPS-QAC-QTP-0001Inspection Test Plan (ITP) for Pipeline InstallationQAQC
Issued06 Mar 2026Rev A
PendingForecast 13 Mar 2026
N/A
PendingForecast 08 May 2026
PendingForecast -
Client return overdueClient return: 13 Mar 2026 / IAF: 08 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QTP-0002Inspection Test Plan (ITP) for Riser and Spools FabricationQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned06 Jun 2026Code 2
ClosedClient return: 13 Nov 2025
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0001Welding Qualification Test Procedure (WQT)QAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned06 Jun 2026Code 1
ClosedClient return: 13 Nov 2025
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0002Welding Procedure Specifications (WPS) for StructureQAQC
Issued14 Jan 2026Rev A
Returned06 Mar 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast 25 May 2026
Final return overdueFinal return: 25 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0003Welding Procedure Specifications (WPS) for Spool Tie-inQAQC
Issued14 Jan 2026Rev A
Returned06 Mar 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast 25 May 2026
Final return overdueFinal return: 25 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0004Weld Repair ProcedureQAQC
Issued08 Feb 2026Rev A
PendingForecast 13 Feb 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 13 Feb 2026 / IAF: 24 Apr 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0005Welding Consumable Control ProcedureQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned06 Jun 2026Code 1
ClosedClient return: 13 Nov 2025
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0006Blasting and Painting ProcedureQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 13 Nov 2025 / IAF: 24 Apr 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-RPT-0001Paint MatrixQAQC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0008Non-Destructive Examination (NDE) Procedure for Tie-in, Seafastening & Minor FabricationQAQC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
Issued14 May 2026Rev 0
PendingForecast 21 May 2026
Final return overdueFinal return: 21 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-RPT-0002NDE MatrixQAQC
Issued22 Apr 2026Rev A
Returned11 May 2026Code A
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0009Non-Conformance Control ProcedureQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned06 Jun 2026Code 1
ClosedClient return: 13 Nov 2025
KURMA MANISQAQCTISB-KRM_RPS-QPR-QAC-0010Corrective Action ProcedureQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned06 Jun 2026Code 1
ClosedClient return: 13 Nov 2025
KURMA MANISQAQCTISB-KRM_RPS-QAC-RPT-0003CV and Qualification Records of NDE PersonnelQAQC
Issued22 Apr 2026Rev A
PendingForecast -
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
KURMA MANISQAQCTISB-KRM_RPS-QAC-QPR-0011Material Control ProcedureQAQC
Issued06 Nov 2025Rev A
PendingForecast 13 Nov 2025
N/A
Issued05 Dec 2025Rev 0
Returned09 Jun 2026Code 2
ClosedClient return: 13 Nov 2025
KURMA MANISHSETISB-KRM_RPS-HSE-HHP-0001HSE PlanHSE
Issued20 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued05 Dec 2025Rev 0
Returned19 Jan 2026Code 0
Closed
KURMA MANISHSETISB-KRM_RPS-HSE-HMP-0001Project HSEMS Bridging DocumentHSE
PendingForecast 23 Jan 2026
PendingForecast -
N/A
PendingForecast 08 May 2026
PendingForecast -
IFR overdueIFR: 23 Jan 2026 / IAF: 08 May 2026
KURMA MANISHSETISB-KRM_RPS-HSE-QPR-0001Offshore Emergency Response PlanHSE
Issued05 May 2026Rev A
PendingForecast 12 May 2026
Returned11 May 2026Code 1
PendingForecast 08 May 2026
PendingForecast -
Client return overdueClient return: 12 May 2026 / IAF: 08 May 2026
KURMA MANISHSETISB-KRM_RPS-HSE-QPR-0002Onshore Emergency Response PlanHSE
Issued07 Apr 2026Rev A
PendingForecast 14 Apr 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 14 Apr 2026 / IAF: 24 Apr 2026
KURMA MANISHSETISB-KRM_RPS-HSE-HHA-0001Project Construction and Installation Risk AssessmentHSE
PendingForecast 20 Feb 2026
PendingForecast -
N/A
PendingForecast 27 Feb 2026
PendingForecast -
IFR overdueIFR: 20 Feb 2026 / IAF: 27 Feb 2026
KURMA MANISHSETISB-KRM_RPS-HSE-HHA-0002Job Hazard AnalysisHSE
Issued02 Mar 2026Rev A
PendingForecast 09 Mar 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 09 Mar 2026 / IAF: 24 Apr 2026
KURMA MANISHSETISB-KRM_RPS-HSE-QPR-0003Scaffolding & Working at Height ProcedureHSE
Issued07 Jan 2026Rev A
PendingForecast 14 Jan 2026
N/A
PendingForecast 24 Apr 2026
PendingForecast -
Client return overdueClient return: 14 Jan 2026 / IAF: 24 Apr 2026
KURMA MANISHSETISB-KRM_RPS-HSE-QPR-0004Waste Management Plan & ProcedureHSE
Issued20 May 2026Rev A
PendingForecast 27 May 2026
N/A
PendingForecast 11 May 2026
PendingForecast -
Client return overdueClient return: 27 May 2026 / IAF: 11 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QMU-0001Line Pipes Manfacturing HandbookTRANSPORTATION & INSTALLATION
Issued14 Feb 2026Rev A
PendingForecast 20 Feb 2026
N/A
PendingForecast 23 Jan 2026
PendingForecast -
Client return overdueClient return: 20 Feb 2026 / IAF: 23 Jan 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QMU-0002Line Pipes Coating HandbookTRANSPORTATION & INSTALLATION
PendingForecast 15 May 2026
PendingForecast -
N/A
PendingForecast 04 May 2026
PendingForecast -
IFR overdueIFR: 15 May 2026 / IAF: 04 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QMU-0003Zap-Lok End Prepration Manfacturing BookTRANSPORTATION & INSTALLATION
PendingForecast 15 May 2026
PendingForecast -
N/A
PendingForecast 06 Mar 2026
PendingForecast -
IFR overdueIFR: 15 May 2026 / IAF: 06 Mar 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-EMS-0001Riser and Spools Fabrication PackageTRANSPORTATION & INSTALLATION
PendingForecast 15 May 2026
PendingForecast -
N/A
PendingForecast 28 Aug 2026
PendingForecast -
IFR overdueIFR: 15 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-EMS-0002Diverless Tie-In System Fabrication PackageTRANSPORTATION & INSTALLATION
PendingForecast 15 May 2026
PendingForecast -
N/A
PendingForecast 27 Mar 2026
PendingForecast -
IFR overdueIFR: 15 May 2026 / IAF: 27 Mar 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0001Zap-Lok Joint Validation Test Procedure ReportTRANSPORTATION & INSTALLATION
Issued13 Mar 2026Rev A
Returned02 Apr 2026Code 1
Returned30 Mar 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0010Zaplok Pipeline Repair ProcedureTRANSPORTATION & INSTALLATION
Issued06 May 2026Rev A
Returned02 Jun 2026Code 2
Returned25 May 2026Code 1
Issued03 Jun 2026Rev 0
PendingForecast -
IAF issued
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0001Vessel Pull Off / Out ProcedureTRANSPORTATION & INSTALLATION
Issued11 Apr 2026Rev A
Returned02 Jun 2026Code 2
Returned19 Apr 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0002Pipeline Offshore Mobilization ProcedureTRANSPORTATION & INSTALLATION
Issued18 May 2026Rev A
Returned02 Jun 2026Code 2
Submitted28 May 2026
PendingForecast 27 Apr 2026
PendingForecast -
MWS return overdueMWS return: 04 Jun 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-RPT-0001Linepipe Transportation and Seafastening AnalysisTRANSPORTATION & INSTALLATION
Issued03 Mar 2026Rev A
Returned16 Mar 2026Code 2
Returned09 Apr 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-QPR-0001Linepipe Transportation and Handling ProcedureTRANSPORTATION & INSTALLATION
Issued25 Apr 2026Rev A
Returned31 May 2026Code 2
Returned29 Apr 2026Code 3
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-RPT-0002Spool & Riser Transportation and Seafastening AnalysisTRANSPORTATION & INSTALLATION
Issued31 Mar 2026Rev A
Returned02 Apr 2026Code 2
Returned08 Apr 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-QPR-0002Spool & Riser Transportation and Handling ProcedureTRANSPORTATION & INSTALLATION
Issued22 May 2026Rev A
Returned02 Jun 2026Code 2
Submitted28 May 2026
PendingForecast 30 Apr 2026
PendingForecast -
MWS return overdueMWS return: 04 Jun 2026 / IAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0002WHP Riser Installation AnalysisTRANSPORTATION & INSTALLATION
Issued04 May 2026Rev A
PendingForecast -
Returned06 May 2026Code 2
Issued16 May 2026Rev 0
Returned27 May 2026Code 3
Closed
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0003WHP Riser Installation ProcedureTRANSPORTATION & INSTALLATION
Issued04 May 2026Rev A
Returned02 Jun 2026Code 3
Returned06 May 2026Code 2
PendingForecast 30 Apr 2026
PendingForecast -
IAF overdueIAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0003Subsea Pipeline Installation AnalysisTRANSPORTATION & INSTALLATION
Issued13 Mar 2026Rev A
Returned02 Jun 2026Code 2
Returned30 Mar 2026Code 2
Issued23 Apr 2026Rev 0
Returned02 Jun 2026Code 2
Closed
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0004Subsea Pipeline Installation ProcedureTRANSPORTATION & INSTALLATION
Issued06 May 2026Rev A
PendingForecast -
Returned19 May 2026Code 2
PendingNo forecast
PendingForecast -
Pending return
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0004Diverless Tie-In Spools Installation AnalysisTRANSPORTATION & INSTALLATION
Issued28 May 2026Rev A
Returned02 Jun 2026Code 2
Submitted28 May 2026
PendingForecast 27 Apr 2026
PendingForecast -
MWS return overdueMWS return: 04 Jun 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0005Diverless Tie-In Spools Installation ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 11 Mar 2026
PendingForecast -
PendingForecast -
PendingForecast 27 Apr 2026
PendingForecast -
IFR overdueIFR: 11 Mar 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0009Anchor Handling ProcedureTRANSPORTATION & INSTALLATION
Issued06 Apr 2026Rev A
Returned02 Jun 2026Code 2
Returned17 Apr 2026Code 2
PendingForecast 27 Apr 2026
PendingForecast -
IAF overdueIAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-RPT-0003Anchor Pattern Procedure and Mooring AnalysisTRANSPORTATION & INSTALLATION
PendingForecast 17 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 30 Apr 2026
PendingForecast -
IFR overdueIFR: 17 Apr 2026 / IAF: 30 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0013Crossing Installation ProcedureTRANSPORTATION & INSTALLATION
PendingNo forecast
PendingForecast -
PendingForecast -
Issued16 May 2026Rev 0
Returned27 May 2026Code 3
Closed
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0007Pre-Lay Survey ProcedureTRANSPORTATION & INSTALLATION
Issued06 Mar 2026Rev A
Returned18 Apr 2026Code 1
Returned30 Mar 2026Code 2
Issued16 Apr 2026Rev 0
Returned06 May 2026Code 0
Closed
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0005Pre-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 24 Apr 2026
PendingForecast -
N/A
PendingForecast 08 May 2026
PendingForecast -
IFR overdueIFR: 24 Apr 2026 / IAF: 08 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0008Barge Management System (BMS) and Tug Management System (TMS) ProcedureTRANSPORTATION & INSTALLATION
Issued16 Apr 2026Rev A
Returned02 Jun 2026Code 2
Submitted27 Apr 2026
PendingForecast 08 May 2026
PendingForecast -
MWS return overdueMWS return: 04 May 2026 / IAF: 08 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0015As -Built Survey ProcedureTRANSPORTATION & INSTALLATION
Issued15 Apr 2026Rev A
PendingForecast 22 Apr 2026
N/A
PendingForecast 29 May 2026
PendingForecast -
Client return overdueClient return: 22 Apr 2026 / IAF: 29 May 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0006Post-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 20 Jul 2026
PendingForecast -
N/A
PendingForecast 03 Aug 2026
PendingForecast -
Pending IFR
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0006Marine Growth Cleaning ProcedureTRANSPORTATION & INSTALLATION
Issued14 Apr 2026Rev A
Returned12 May 2026Code 1
N/A
Issued18 May 2026Rev 0
Returned02 Jun 2026Code 4
Closed
KURMA MANIST&ITISB-KRM_RPS-NAV-ELA-0002Mermaid Resiliant Anchor Pattern at KUJT-A for Pipeline Start-UpTRANSPORTATION & INSTALLATION
Issued22 Apr 2026Rev A
PendingForecast 29 Apr 2026
Returned04 May 2026Code 1
PendingForecast 27 Apr 2026
PendingForecast -
Client return overdueClient return: 29 Apr 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-ELA-0003Mermaid Resiliant Anchor Pattern for Pipeline InstallationTRANSPORTATION & INSTALLATION
Issued22 Apr 2026Rev A
PendingForecast 29 Apr 2026
Returned04 May 2026Code 1
PendingForecast 27 Apr 2026
PendingForecast -
Client return overdueClient return: 29 Apr 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-ELA-0004Mermaid Resiliant Anchor Pattern at Kurma Manis for Pipeline LaydownTRANSPORTATION & INSTALLATION
Issued22 Apr 2026Rev A
PendingForecast 29 Apr 2026
Returned04 May 2026Code 1
PendingForecast 27 Apr 2026
PendingForecast -
Client return overdueClient return: 29 Apr 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-NAV-ELA-0007Mermaid Resiliant Anchor Pattern for Riser Installation at KUJT-A PlatformTRANSPORTATION & INSTALLATION
Issued28 May 2026Rev A
PendingForecast 04 Jun 2026
Submitted28 May 2026
PendingNo forecast
PendingForecast -
Client return overdueClient return: 04 Jun 2026 / MWS return: 04 Jun 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0014Rigid Pipeline Pre-Commissioning ProcedureTRANSPORTATION & INSTALLATION
Issued24 May 2026Rev A
Returned02 Jun 2026Code 2
Submitted28 May 2026
PendingForecast 27 Apr 2026
PendingForecast -
MWS return overdueMWS return: 04 Jun 2026 / IAF: 27 Apr 2026
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0016Overall System Test and Pre-CommissioningTRANSPORTATION & INSTALLATION
Issued24 May 2026Rev A
Returned02 Jun 2026Code 2
N/A
PendingForecast 02 Oct 2026
PendingForecast -
Pending IAF
KURMA MANIST&ITISB-KRM_RPS-PIL-RPT-0007PIG Loading and Inspection ReportTRANSPORTATION & INSTALLATION
PendingForecast 19 Sep 2026
PendingForecast -
N/A
PendingForecast 02 Oct 2026
PendingForecast -
Pending IFR
KURMA MANIST&ITISB-KRM_RPS-PIL-QPR-0012Intelligent PIG (IP) Baseline Survey ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 30 Mar 2026
PendingForecast -
N/A
PendingForecast 27 Apr 2026
PendingForecast -
IFR overdueIFR: 30 Mar 2026 / IAF: 27 Apr 2026
BERANTAI EASTPMTTISB-BEF6_FPS-PMT-QEP-0001Project Execution Plan (PEP)PROJECT MANAGEMENT
Issued19 Sep 2025Rev A
PendingForecast 26 Sep 2025
N/A
Issued03 Dec 2025Rev 0
Returned02 Jan 2026Code 0
ClosedClient return: 26 Sep 2025
BERANTAI EASTPMTTISB-BEF6_FPS-PMT-RPT-0001Planning PackagePROJECT MANAGEMENT
Issued12 Feb 2026Rev A
Returned15 Mar 2026Code A
N/A
Issued22 Apr 2026Rev 0
Returned01 May 2026Code 4
Closed
BERANTAI EASTPMTTISB-BEF6_FPS-PMT-RPT-0002Project SchedulePROJECT MANAGEMENT
Issued19 Sep 2025Rev A
PendingForecast 26 Sep 2025
N/A
Issued23 Dec 2025Rev 0
PendingForecast 30 Dec 2025
Client return overdueClient return: 26 Sep 2025 / Final return: 30 Dec 2025
BERANTAI EASTPMTTISB-BEF6_FPS-PMT-QPR-0001Final Documentation ProcedurePROJECT MANAGEMENT
Issued05 Oct 2025Rev A
PendingForecast 10 Oct 2025
N/A
Issued14 Nov 2025Rev 0
PendingForecast 21 Nov 2025
Client return overdueClient return: 10 Oct 2025 / Final return: 21 Nov 2025
BERANTAI EASTPMTTISB-BEF6_FPS-PMT-MDR-0001Master Deliverables RegisterPROJECT MANAGEMENT
Issued12 Sep 2025Rev A
PendingForecast 19 Sep 2025
N/A
Issued24 Oct 2025Rev 0
Returned02 Jan 2026Code 0
ClosedClient return: 19 Sep 2025
BERANTAI EASTPROTISB-BEF6_FPS-SCM-QPR-0001Procurement Plan and ProcedurePROCUREMENT
Issued10 Oct 2025Rev A
PendingForecast 17 Oct 2025
N/A
Issued08 Dec 2025Rev 0
PendingForecast 15 Dec 2025
Client return overdueClient return: 17 Oct 2025 / Final return: 15 Dec 2025
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QQP-0001Project Quality Plan (PQP)QAQC
Issued19 Sep 2025Rev A
PendingForecast 26 Sep 2025
N/A
Issued30 Oct 2025Rev 0
PendingForecast 06 Nov 2025
Client return overdueClient return: 26 Sep 2025 / Final return: 06 Nov 2025
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QTP-0001Inspection Test Plan (ITP) for Pipeline InstallationQAQC
Issued27 Feb 2026Rev A
Returned11 May 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast 25 May 2026
Final return overdueFinal return: 25 May 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QTP-0002Inspection Test Plan (ITP) for Flexible Pipeline ManufacturingQAQC
Issued27 Feb 2026Rev A
Returned11 May 2026Code B
N/A
PendingForecast 29 Apr 2026
Returned11 May 2026Code 1
ClosedIAF: 29 Apr 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QTP-0003Inspection Test Plan (ITP) for Ancillaries (Buoncy Module)QAQC
Issued27 Feb 2026Rev A
Returned11 May 2026Code A
N/A
Issued18 May 2026Rev 0
PendingForecast 25 May 2026
Final return overdueFinal return: 25 May 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QTP-0004Inspection Test Plan (ITP) for Ancillaries (Bend Stiffner)QAQC
Issued29 Apr 2026Rev A
Returned11 May 2026Code C
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-RPT-0001Factory Acceptance Test (FAT)QAQC
Issued26 Dec 2025Rev A
PendingForecast 02 Jan 2026
N/A
PendingForecast 30 Apr 2026
PendingForecast -
Client return overdueClient return: 02 Jan 2026 / IAF: 30 Apr 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0001Handling and Storage ProcedureQAQC
Issued26 Dec 2025Rev A
PendingForecast 02 Jan 2026
N/A
PendingForecast 30 Apr 2026
PendingForecast -
Client return overdueClient return: 02 Jan 2026 / IAF: 30 Apr 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0002Reel and Reel Drive Unit Interface ProcedureQAQC
Issued29 Apr 2026Rev A
PendingForecast -
N/A
PendingForecast 08 May 2026
PendingForecast -
IAF overdueIAF: 08 May 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0003Flexible Pipeline Repair ProcedureQAQC
Issued13 Feb 2026Rev A
PendingForecast 20 Feb 2026
N/A
PendingForecast 30 Apr 2026
PendingForecast -
Client return overdueClient return: 20 Feb 2026 / IAF: 30 Apr 2026
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0004Non-Destructive Examination (NDE) Procedure for Tie-in, Seafastening & Minor FabricationQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code B
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-RPT-0002NDE MatrixQAQC
Issued06 Mar 2026Rev A
Returned28 Apr 2026Code A
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0005Blasting and Painting ProcedureQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code A
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0006Welding Procedure and Specification (WPS) for StructuralQAQC
Issued17 Apr 2026Rev A
PendingForecast -
N/A
Issued13 May 2026Rev 0
Returned20 May 2026
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0007Paint MatrixQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code A
N/A
Issued13 May 2026Rev 0
Returned20 May 2026
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0008Welding Consumable Control ProcedureQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code A
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QPR-0009Weld Repair ProcedureQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code A
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTQAQCTISB-BEF6_FPS-QAC-QTP-0005Inspection and Test Plan for StructureQAQC
Issued17 Apr 2026Rev A
Returned28 Apr 2026Code B
N/A
Issued06 May 2026Rev 0
Returned11 May 2026Code 1
Closed
BERANTAI EASTHSETISB-BEF6_FPS-HSE-HHP-0001HSE PlanHSE
Issued20 Nov 2025Rev A
Returned13 Jan 2026Code A
N/A
Issued04 Dec 2025Rev 0
Returned19 Feb 2026Code 0
Closed
BERANTAI EASTHSETISB-BEF6_FPS-HSE-HMP-0001Project HSEMS Bridging DocumentHSE
PendingForecast 01 May 2026
PendingForecast -
N/A
PendingForecast 08 May 2026
PendingForecast -
IFR overdueIFR: 01 May 2026 / IAF: 08 May 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-QPR-0001Offshore Emergency Response PlanHSE
Issued05 May 2026Rev A
PendingForecast -
Submitted09 Jun 2026
PendingForecast 13 Feb 2026
PendingForecast -
IAF overdueIAF: 13 Feb 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-QPR-0002Onshore Emergency Response PlanHSE
Issued08 Apr 2026Rev A
PendingForecast -
N/A
PendingForecast 24 Apr 2026
PendingForecast -
IAF overdueIAF: 24 Apr 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-HHA-0001Project Construction and Installation Risk AssessmentHSE
PendingForecast 27 Apr 2026
PendingForecast -
N/A
PendingForecast 11 May 2026
PendingForecast -
IFR overdueIFR: 27 Apr 2026 / IAF: 11 May 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-HHA-0002Job Hazard AnalysisHSE
Issued27 Feb 2026Rev A
PendingForecast 06 Mar 2026
N/A
PendingForecast 08 May 2026
PendingForecast -
Client return overdueClient return: 06 Mar 2026 / IAF: 08 May 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-QPR-0003Scaffolding & Working at Height ProcedureHSE
Issued09 Jan 2026Rev A
PendingForecast 16 Jan 2026
N/A
PendingForecast 13 Feb 2026
PendingForecast -
Client return overdueClient return: 16 Jan 2026 / IAF: 13 Feb 2026
BERANTAI EASTHSETISB-BEF6_FPS-HSE-QPR-0004Waste Management Plan & ProcedureHSE
Issued20 May 2026Rev A
PendingForecast -
N/A
PendingForecast 24 Apr 2026
PendingForecast -
IAF overdueIAF: 24 Apr 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-RPT-0001WHP Winch Base and Pull-in Aids Design Report Pull-in Routing & Design ReportTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-RPT-0002FPSO Winch Base and Pull-in Aids Design Report Pull-in Routing & Design ReportTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-RPT-0001Flexible Lay spread System Sea Fastening Design and Transportation Analysis ReportTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-RPT-0003Flexible Reel Lifting Analysis including Lifting Plan for Port LiftingTRANSPORTATION & INSTALLATION
Issued13 Apr 2026Rev A
PendingForecast 20 Apr 2026
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-RPT-0001Berantai Static Flexible Pipeline Installation AnalysisTRANSPORTATION & INSTALLATION
Issued14 May 2026Rev A
Returned08 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-RPT-0002Dynamic Flexible Pipeline Installation Analysis ReportTRANSPORTATION & INSTALLATION
Issued22 May 2026Rev A
Returned08 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPL-0001Flexible Pipeline Mobilization PlanTRANSPORTATION & INSTALLATION
Issued29 Apr 2026Rev A
PendingForecast 06 May 2026
Returned06 May 2026Code 2
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 06 May 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-QPR-0001WHP and FPSO Flexible Risers Hang-Off and Tie-in ProcedureTRANSPORTATION & INSTALLATION
Issued29 Apr 2026Rev A
Returned18 May 2026Code A
Returned06 May 2026Code 3
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-QPR-0002Winch Load Test ProcedureTRANSPORTATION & INSTALLATION
Issued17 Apr 2026Rev A
PendingForecast 24 Apr 2026
Returned06 May 2026Code 2
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 24 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0001Berantai East Flexible Installation Procedure including J-tube pull at BE-WHP and 2nd Pull End at FPSOTRANSPORTATION & INSTALLATION
Issued29 Apr 2026Rev A
Returned12 May 2026Code 2
Returned06 May 2026Code 3
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0002Flexible I-tube Installation and Hook-Up ProcedureTRANSPORTATION & INSTALLATION
Issued25 May 2026Rev A
Returned08 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-QPL-0001MOS and Lifting Plan for Reel Loading Operation at PortTRANSPORTATION & INSTALLATION
Issued24 May 2026Rev A
PendingForecast 29 May 2026
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 29 May 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-QPR-0001Weather Monitoring & Emergency Pull-Out ProcedureTRANSPORTATION & INSTALLATION
Issued04 Jun 2026Rev A
Returned08 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-SUB-QPR-0001FOC Termination, Isolation and Disconnection ProcedureTRANSPORTATION & INSTALLATION
Issued14 May 2026Rev A
PendingForecast 21 May 2026
Submitted09 Jun 2026
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 21 May 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-SUB-QPR-0002FOC Retrieval ProcedureTRANSPORTATION & INSTALLATION
Issued14 May 2026Rev A
PendingForecast 21 May 2026
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 21 May 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0001Flexible Lay Spread and Sea Fastening DesignTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0002Berantai East Pull-in Winch Tie-down Details DrawingsTRANSPORTATION & INSTALLATION
Issued22 May 2026Rev A
Returned09 Jun 2026Code 2
Submitted09 Jun 2026
PendingForecast 15 May 2026
PendingForecast -
IAF overdueIAF: 15 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0003FPSO Pull-in Winch Tie-Down Details DrawingsTRANSPORTATION & INSTALLATION
PendingForecast 12 Jun 2026
PendingForecast -
PendingForecast -
PendingForecast 15 May 2026
PendingForecast -
IAF overdueIAF: 15 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-ELA-0001Installation Sequence including Startup & 2nd End PullTRANSPORTATION & INSTALLATION
PendingForecast 12 Jun 2026
PendingForecast -
PendingForecast -
PendingForecast 15 May 2026
PendingForecast -
IAF overdueIAF: 15 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-ELA-0002Flexible Berantai East J-Tube Pull-in Arrangement DrawingsTRANSPORTATION & INSTALLATION
PendingForecast 12 Jun 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-ELA-0003Flexible FPSO I-Tube Pull-in Arrangement DrawingsTRANSPORTATION & INSTALLATION
PendingForecast 12 Jun 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-ELA-0004Flexible I-Tube Installation Arrangement DrawingsTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0004Rigging Arrangement Details for Pull-in, Abandonment & Frecovery and others.TRANSPORTATION & INSTALLATION
Issued11 Jun 2026Rev A
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IAF overdueIAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0005397.9 MT. & 121.1 MT. Flexible Pipeline Reel Lifting ArrangementTRANSPORTATION & INSTALLATION
Issued13 Apr 2026Rev A
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-ELA-0001Vessel Setup for Start Pull at BE-WHP and FPSO 2nd End PullTRANSPORTATION & INSTALLATION
PendingForecast 22 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 22 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-ELA-0002Vessel Setup for Lazy Loop Lay, Abandonment & Recovery and Temporary Laydown of 2nd End Pull HeadTRANSPORTATION & INSTALLATION
PendingForecast 24 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 24 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0006Crossing Material Installation Rigging Detail, Work Sequence and othersTRANSPORTATION & INSTALLATION
PendingForecast 24 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 24 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-STR-EDE-0007Vessel to WHP and FPSO Handshake Rigging ArrangementTRANSPORTATION & INSTALLATION
PendingForecast 24 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 24 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-ELA-0005Crossing Arrangements DrawingsTRANSPORTATION & INSTALLATION
PendingForecast 24 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 24 Apr 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-RPT-0002Flexible Pipeline, Ancillaries & Mattress Transportation and Seafastening AnalysisTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0003Flexible Pipeline, Ancillaries & Mattress Transportation, Handling and Mobilization ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0004Pre-Lay Survey ProcedureTRANSPORTATION & INSTALLATION
Issued06 Mar 2026Rev A
Returned18 Apr 2026Code 1
N/A
Issued16 Apr 2026Rev 0
PendingForecast 23 Apr 2026
Final return overdueFinal return: 23 Apr 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-RPT-0003Pre-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 08 May 2026
PendingForecast -
N/A
PendingForecast 22 May 2026
PendingForecast -
IFR overdueIFR: 08 May 2026 / IAF: 22 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0005Barge Management System (BMS) ProcedureTRANSPORTATION & INSTALLATION
Issued16 Apr 2026Rev A
PendingForecast 23 Apr 2026
N/A
PendingForecast 18 May 2026
PendingForecast -
Client return overdueClient return: 23 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0006Survey Procedure Manual (Post-Lay-Berantai East)TRANSPORTATION & INSTALLATION
Issued15 Apr 2026Rev A
Returned08 Jun 2026Code 2
N/A
PendingForecast 18 May 2026
PendingForecast -
IAF overdueIAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-RPT-0004Post-Lay Survey ReportTRANSPORTATION & INSTALLATION
PendingForecast 06 Oct 2026
PendingForecast -
N/A
PendingForecast 20 Oct 2026
PendingForecast -
Pending IFR
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0007Flexible Pipeline Pre-Commissioning and Annulus Test ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 27 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 27 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0008Overall System Test and Pre-CommissioningTRANSPORTATION & INSTALLATION
PendingForecast 27 Apr 2026
PendingForecast -
N/A
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 27 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-PIL-QPR-0009Dewatering PIG Loading ProcedureTRANSPORTATION & INSTALLATION
PendingForecast 27 Apr 2026
PendingForecast -
PendingForecast -
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 27 Apr 2026 / IAF: 18 May 2026
BERANTAI EASTT&ITISB-BEF6_FPS-NAV-EGA-0001Vessel General Layout and Deck Arrangements Drawings for MPSVTRANSPORTATION & INSTALLATION
PendingForecast 20 Apr 2026
PendingForecast -
N/A
PendingForecast 18 May 2026
PendingForecast -
IFR overdueIFR: 20 Apr 2026 / IAF: 18 May 2026