Vessel Movement

Campaign Window01 Jun - 25 Oct147 calendar days
Vessels4specific vessel lanes from schedule hierarchy
Campaign Periods4area vessel windows
Movement Activities1560 critical activities
Next Movement06 JunPACKAGE A - EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
RIG

RIG

01 Jun - 01 Jun
1 days
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 0 activities
01 Jun - 01 Jun
PACKAGE A

KURMA MANIS

06 Jun - 27 Sept
114 days
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 66 activities
06 Jun - 27 Sept
PACKAGE A

IRONG TIMUR

12 Jun - 12 Sept
93 days
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 75 activities
12 Jun - 12 Sept
PACKAGE B

BERANTAI EAST

15 Jul - 25 Oct
103 days
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 15 activities
15 Jul - 25 Oct

Movement Overview

Project Movement Navigator

Overall campaign timeline from start to completion. Scroll the detail grid to zoom the focus window.

Focus windowScroll flow board to move the focus window
Show in timeline
Jun 2026Jul 2026Aug 2026Sept 2026Oct 2026
RIGRIG
PACKBERANTAI EAST
PACKIRONG TIMUR
PACKKURMA MANIS

Movement Detail

Campaign Activity Flow

Detailed sequence from port readiness through offshore execution and demobilization.

Other
Rig-UpPACKAGE A - KURMA MANIS / EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 / 06 Jun 2026 to 12 Jun 2026 / 7 days
Vessel
Area
Mon01JunTue02JunWed03JunThu04JunFri05JunSat06JunSun07JunMon08JunTue09JunWed10JunThu11JunFri12JunSat13JunSun14JunMon15JunTue16JunWed17JunThu18JunFri19JunSat20JunSun21JunMon22JunTue23JunWed24JunThu25JunFri26JunSat27JunSun28JunMon29JunTue30JunWed01JulThu02JulFri03JulSat04JulSun05JulMon06JulTue07JulWed08JulThu09JulFri10JulSat11JulSun12JulMon13JulTue14JulWed15JulThu16JulFri17JulSat18JulSun19JulMon20JulTue21JulWed22JulThu23JulFri24JulSat25JulSun26JulMon27JulTue28JulWed29JulThu30JulFri31JulSat01AugSun02AugMon03AugTue04AugWed05AugThu06AugFri07AugSat08AugSun09AugMon10AugTue11AugWed12AugThu13AugFri14AugSat15AugSun16AugMon17AugTue18AugWed19AugThu20AugFri21AugSat22AugSun23AugMon24AugTue25AugWed26AugThu27AugFri28AugSat29AugSun30AugMon31AugTue01SeptWed02SeptThu03SeptFri04SeptSat05SeptSun06SeptMon07SeptTue08SeptWed09SeptThu10SeptFri11SeptSat12SeptSun13SeptMon14SeptTue15SeptWed16SeptThu17SeptFri18SeptSat19SeptSun20SeptMon21SeptTue22SeptWed23SeptThu24SeptFri25SeptSat26SeptSun27SeptMon28SeptTue29SeptWed30SeptThu01OctFri02OctSat03OctSun04OctMon05OctTue06OctWed07OctThu08OctFri09OctSat10OctSun11OctMon12OctTue13OctWed14OctThu15OctFri16OctSat17OctSun18OctMon19OctTue20OctWed21OctThu22OctFri23OctSat24OctSun25Oct
RIG
RIG01 Jun - 01 Jun
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
01 Jun - 01 Jun
PACK
KURMA MANIS06 Jun - 27 Sept
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
06 Jun - 27 Sept
PACK
IRONG TIMUR12 Jun - 12 Sept
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
12 Jun - 12 Sept
PACK
BERANTAI EAST15 Jul - 25 Oct
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
15 Jul - 25 Oct

Campaign Timeline

Vessel Movement by Period

01 Jun 2026 to 25 Oct 2026 from schedule data

MPSVDLBRIGBarge / AHTSPort / LoadoutInstallationSurvey / SpoolCritical
Jun 2026
Jul 2026
Aug 2026
Sept 2026
Oct 2026
Current
RIG : RIGEPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 01 Jun to 01 Jun
PortTransitSurvey / SpoolInstallationDemobOther
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
PACKAGE A : KURMA MANISEPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 06 Jun to 27 Sept
PortTransitSurvey / SpoolInstallationDemobOther
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
Rig-Up
Jacket Cleaning
Escort MB #2 to Field KM
MB : Sliding Clamp Complete Fabrication + Sailaway + Dressup and Tie-Down Riser and Clamp @ KUJTA
IT : Pipeline Support @ IT
Support with DLB
Support for Pipeline Operational @ KM
Support for Pipeline Operational @ KM
Pipeline Support @ KM
Pipeline Support @ KM
Pipe Laying (2.5KM/day)
Demob to Kuantan Port & Demob etc
PACKAGE A : IRONG TIMUREPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 12 Jun to 12 Sept
PortTransitSurvey / SpoolInstallationDemobOther
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
Jacket Cleaning
Rigup ROV + ADS + Concrete Matteres + Sleepers + RSAS + Survey Loadout
Seafastening
Riser Final Fabrication and HT (DOSH) BWHP & KUJT-A onboard Transportation Barge
Vessel At Site
Rigup ZAPLOK Press Machine
KM : Sailaway to KM + Vessel arrival Readiness & Pre- Survey + Mattress @ KM
Support with DLB
Support for Pipeline Operational @ IT
Pipeline Support @ IT
KM : Riser Works at KUJT-A + Demob to IT
Rig-Up
Rigup Campaign by VPSB
Support for Pipeline Operational @ IT
Pipeline Support @ KM
PACKAGE B : BERANTAI EASTEPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616 - 15 Jul to 25 Oct
PortTransitSurvey / SpoolInstallationDemobOther
EPCIC PIPELINE SYSTEM VESTIGO PACKAGE A & B - OFFSHORE EXECUTION as of 20260616
Loadout of , Reel Drive system, tensioner at Johor Port and MWS Aprroval
Rig-Up